The Stefanutti Stocks civils team is making steady progress on Kassier Rd upgrade between the M13 and the Westown Construction site. The extensive roadworks along this stretch are to allow…
Yesterday, 24th September the Kassier Rd construction team led by Stefanutti Stocks and SMEC reached another milestone with the first bridge concrete pour for the new bridge over Kassier Rd!…
As the Kassier Rd bridge building progresses, our team has started laying down the bottom steel mat and prestressing the tendons of this 66 m-long connector. Now in superstructure or…
M13 Road Closure – On Wednesday 10th July 2024 from 05:00 to 15:00 the M13 at Kassier Rd will be closed in both directions. The road closure is in place…
On Thursday 18 April, eThekwini Mayor Councillor Mxolisi Kaunda joined various stakeholders on-site to see first-hand the visible benefit of the municipality’s investment into bulk infrastructure around Westown. With just…
As of 15 March 2024, the Kassier Rd Phase 1B bypass road between the M13 and N3 is now open. This bypass enables the uninterrupted upgrade of this section of…
Momentum is increasing on the eThekwini Municipality’s upgrade of the next phase of Kassier Rd namely the PHASE 1B BYPASS road and the construction of the NEW BRIDGE over the…
The first vertical support structure (also known as a pier) has been completed for the raised access bridge into Westown from the north. This bridge will run over Kassier Rd…
With the last of the heavy rain behind us, the Stefanutti Stocks road contractors began repairing the potholes on the old Kassier Rd, between the M13 and the K9 unit…
Next phase of Kassier upgrade complete – Part 1 of Phase 1B which is the bypass road from the N3 to the SAPS K9 Unit entrance. This temporary bypass road…