Momentum is increasing on the eThekwini Municipality’s upgrade of the next phase of Kassier Rd namely the PHASE 1B BYPASS road and the construction of the NEW BRIDGE over the M13.
KASSIER RD PHASE 1B BYPASS
- The Kassier Rd Phase 1B bypass road between the M13 and N3 will open in early March 2024.
- The bypass will enable the uninterrupted upgrade of Kassier Rd between the N3 and M13 for completion in early 2025.
- Gentle speed humps will be implemented along this stretch of road for traffic calming.
- Stop signs will be installed at the Cliffdale/Engen intersection and entrances to Durban Shongweni Club (DSC).
TRAFFIC DIVERSION ON THE M13
- From early March 2024, traffic deviations will be in place on the M13 both East & West of the Assagay/ Hillcrest/ Shongweni interchange to Kassier Rd.
- This will see traffic deviate onto one side of the M13 for single-lane traffic flow in both directions.
- The deviation will run between 07:00-17:00 on weekdays and will be in place until the completion of the bridge construction in early 2025.
The road upgrade momentum is increasing – click here for more information on the overall road upgrade programme.